Procurement Timelinefor the Competitive Purchase of Service Method of Procurement (RFP)Amended October 3, 2006 |
Note: The following dates on the timeline have been amended:
| Amended from | New date | |
| Public notice | October 10, 2006 | October 18, 2006 |
| Proposal submittal | January 12, 2007 | January 26, 2007 |
This coordinated timeline allows applicants to plan accordingly, ensuring quality proposals and maximum competition. It is one of many resources available to assist applicants competing for state contracts.
Procurement notices are centrally located at www.spo.hawaii.gov, click Procurement Notices. Notices of Requests for Information (RFI) are also available on the same website. An RFI is issued prior to the RFP for the purpose of obtaining feedback. Participation in the RFI process by providers and interested parties is essential in ensuring the most efficient and appropriate services are contracted.
This timeline is to plan and coordinate the request for proposals (RFP) process among state purchasing agencies for solicitations published between October and December 2006 for contracts effective on or after July 1, 2007.
See other resources for health and human service providers and interested parties.
| Activity | Dates |
| Consolidated Report of Planned Purchases by SPO | January 2006 |
| Planning Activities |
January – September 2006 (Reference: Chapter 3-142, HAR) |
| Requests for Information |
January –September 2006 (Reference: Section 3-142-202, HAR ) |
| Public Notice Announcing RFPs | October 18, 2006 |
| Availability of RFPs | October 18, 2006 – January 26, 2007 |
| RFP Orientation Sessions |
October – Early November 2006 (Reference: Section 3-143-203, HAR) |
|
Addenda to RFPs (As Needed) |
Within ten working days prior to or within a sufficient time before the submittal deadline. (Reference: Section 3-143-301, HAR) |
|
Submission of Questions by Applicants Before Submittal Deadline (As Needed) |
Within a reasonable time before submittal deadline. (Reference: Section 3-143-402, HAR) |
|
Response to Applicants’ Questions (As Needed) |
State Agencies shall promptly respond (Reference: Section 3-143-402, HAR) |
| Proposal Submittal Deadline |
January 26, 2007 (Reference: Section 3-143-204, HAR) |
|
Register of Proposals |
Within 10 working days or a reasonable time after proposal submittal deadline (Reference: Section3-143-615, HAR) |
|
Proposal Evaluation Period |
Late January - March 2007 (Reference: Section 3-143-205, HAR) |
|
Final Revised Proposals (As Needed) |
Late January - February 2007 (Reference: Section 3-143-607, HAR) |
|
Provider Selection and Award |
March - April 2007 (Reference: Section 3-143-205, 3-143-206, HAR) |
|
Notice of Statements of Finding and Decision to Applicants |
March - April 2007 (Reference: Section 3-143-303, HAR) |
|
Protest and Request for Reconsideration (As Needed) |
March - Early May 2007 (Reference: Chapter 148, HAR) |
|
Contract Development |
March - Mid May 2007 (Reference: Chapter 149, HAR) |
|
Contract Mailed to Provider for Signature |
On or about May 16, 2007 |
|
Contract Executed |
On or about June 22, 2007 |
|
Contract Start Date |
July 1, 2007 |
Please direct questions to Mara Smith at 808 587-4704 or mara.smith@hawaii.gov or Corinne Higa at 808 587-4706 or corinne.y.higa@hawaii.gov.
SPO ~ Procurement of Health & Human Services (SPOH) Home
State Procurement Office (SPO) Home
Problems with this web page? Contact the us.
State Procurement Office ~ 1151 Punchbowl Street, #230A ~ Honolulu, HI 96813 ~ Fax: 808.587.4703